Certificate of inspection of emergency lighting of the building. Certificate of checking the lighting network for correct ignition of internal lighting


Inspections and tests of lighting in enterprises.

Periodic inspection and preventive maintenance of lighting installation equipment and devices create all conditions for reliable operation of the lighting network and personnel safety.

When inspecting and checking the lighting network, you should check:

Integrity of panels, lamps and lenses for them, switches, knife switches, sockets, fuses, cartridges and correct installation:

A) lighting panels installed at an accessible height must be in casings with closing doors;

b) protective covers of switches must meet safety requirements,

c) switches, sockets and fuses must have intact covers;

V) lampholders in lamps, and in lampholders, current-carrying and fastening parts must be securely fastened, a phase wire is connected to the contact at the bottom of the lampholder, and a neutral wire is connected to the thread of the lampholder;

G) lamps must have unbroken lenses and reflectors, and the wires leading to the lamps must be secured.

All main switches (switches, circuit breakers) and fuses of the lighting network must have inscriptions with the name of the connection and the current value of the fuse-link. Circuit breakers and fuses must be selected in accordance with the requirements of the PUE.

Reliability and cleanliness of contacts on panels, switches, switches, sockets, fuses and grounding networks. The contacts must be tight and not overheat. Burnt contacts must be cleaned or replaced with new ones.

Condition of branches and wire insulation:

A) branch boxes must have covers,

b) reliable contacts in the network must be ensured,

V) The wire insulation must be intact.

You should pay attention to the condition of the insulation of wires used to enter lamps and devices (switches, plug sockets, etc.). These wires should not experience tension and should be protected from friction at the entry points.

Integrity of portable lamps and step-down transformers:

A) the design of the portable lamp must satisfy all safety requirements,

b) the portable (or stationary) transformer must have a closed, undamaged casing, the housing and the low voltage winding of the transformer must be reliably grounded,

V) Wires of portable lamps and transformers must be protected from mechanical damage.

Correct operation of the emergency lighting network.

It is necessary to carefully check the readiness for action of all network elements. All emergency lighting fixtures must be in good condition, must be equipped with lamps of the required power and have distinctive signs.

Correct operation of the automatic emergency lighting switch. The correct switching of the machine is checked when the AC line supplying it is turned off by a switch.

Correspondence of the power of lamps installed in luminaires to the project. The power of the lamps must correspond to the design in order to ensure the standards of illumination of rooms and workplaces.

The use of lamps with a power greater than the design of a particular lamp is also not allowed, since this leads to overheating of the lamp, socket and wires and can lead to destruction of the diffuser and damage to the insulation of the wires.

The electrician on duty must have drawings or lists of objects indicating the power of the lamps in accordance with the design or calculation, taking into account the required illumination standards.

The value of the network insulation resistance. The insulation resistance value of the lighting network in the area between two adjacent fuses or other protective devices, or behind the last fuse or other protective device, between any wire and ground, as well as between any two wires must be at least 500 kOhm.

When measuring insulation resistance, it is necessary to unscrew the lamps and remove the fuse links, and plug sockets, switches and panel boards must be connected to the network.

The illumination levels in all workshops and main workplaces should not be less than the standardized values.

All results of inspections and testing of the lighting network are recorded in reports signed by the persons who carried out the inspection. The acts are approved by the chief engineer of the enterprise.

Operation of lighting electrical installations

When there is insufficient lighting in production workshops, vision deteriorates, labor productivity drops, and the quality of the products decreases. Therefore, minimum illumination standards provided for by SNiP and PUE have been developed and are mandatory for industrial enterprises.

The illumination values ​​according to these standards depend on the nature of production and the higher the greater the accuracy required when performing technological processes and production operations. When designing and lighting calculations, illumination is assumed to be slightly greater than required by standards.

This reserve is determined by the fact that during operation the level of initial (design) illumination inevitably decreases over time. This occurs due to a gradual decrease in the luminous flux of lamps, contamination of fittings and some other reasons. However, the illumination reserve taken during design and calculations is sufficient for normal operation of electric lighting installations: regular cleaning of lamps, light guides, timely change of lamps, etc. If the operation is unsatisfactory, the accepted supply of illumination cannot compensate for the decreasing level of illumination, and it becomes insufficient.

It should be borne in mind that the illumination of the room is greatly influenced by the color of the walls and ceilings and their condition. Painting in light colors and regularly cleaning from dirt helps to ensure the required lighting standards.

The frequency of inspections of lighting electrical installations depends on the nature of the premises, the state of the environment and is established by the chief power engineer of the enterprise. Approximately for dusty rooms with an aggressive environment, the required frequency of inspection of working lighting can be taken once every two months, and in rooms with a normal environment - once every four months. For emergency lighting installations, inspection times are reduced by half.

Inspections and tests of lighting installations.

During operation, electric lighting installations are subjected to a number of checks and tests. Check the insulation resistance of working and emergency lighting. The serviceability of the emergency lighting system is checked by turning off the working lights at least once a quarter. The automatic switch or emergency lighting switch unit is checked once a week during the daytime. For stationary transformers with a voltage of 12-36 V, the insulation is tested once a year, and for portable transformers and lamps with a voltage of 12-36 V - every three months.

Performing photometric measurements of indoor illumination.

Photometric measurements of illumination in the main production and technological workshops and premises with monitoring of lamp power compliance with the design and calculations are carried out once a year. Illumination is checked using a lux meter in all production workshops and at main workplaces. The obtained illumination values ​​must correspond to the calculated and design ones.

Before you begin checking the illumination, it is necessary to establish the places where it is advisable to measure the illumination. The results of inspections and checks are documented in acts approved by the chief power engineer of the enterprise. Features of operation of gas-discharge light sources

Features of the operation of fluorescent lamps and high-pressure gas-discharge lamps.

The industry produces the following gas-discharge light sources with lamps:

  • low pressure fluorescent mercury;
  • high-pressure mercury arc (DRL type);
  • xenon (DKsT type) high pressure air-cooled and ultra-high pressure water-cooled;
  • high and low pressure sodium lamps.

The first two types of lamps are most widespread.

Gas discharge lamps have the following main features. The luminous efficiency (efficiency) of incandescent lamps is in the range of 1.6-3%, and their luminous efficiency does not exceed 20 lm/W of power consumption for high-power lamps and is reduced to 7 lm/W for lamps with a power of up to 60 W. The luminous efficiency of fluorescent lamps and DRL lamps reaches 7%, and the luminous efficiency exceeds 40 lm/W. However, such lamps are connected to the electrical network only through ballasts (ballasts).

It takes some time to light a fluorescent lamp and especially a DRL lamp (from 5 s to 3 - 10 min). The main element of the ballast is usually an inductive reactor (reactor), which worsens the power factor; Therefore, capacitors are used that are built into modern ballasts.

The industry produces general-purpose fluorescent lamps with power ranging from 4 to 200 W. Lamps with a power from 15 to 80 W are mass-produced in accordance with GOST standards. The remaining lamps are manufactured in small batches according to the appropriate technical specifications. One of the features of using fluorescent lighting is that it is more difficult to troubleshoot compared to using incandescent lamps. This is explained by the fact that the most common circuit for switching on fluorescent lamps contains a starter and a choke (ballast resistance) and becomes much more complex than the switching circuit for an incandescent lamp.

Another feature of fluorescent lighting is that for normal ignition and operation of a fluorescent lamp, the mains voltage should not be less than 95% of the nominal one. Therefore, when operating fluorescent lamps, it is necessary to control the network voltage. Normal operation of a fluorescent lamp is ensured at a temperature of 18–25 °C; at a lower temperature, the fluorescent lamp may not light up.

During operation, fluorescent lamps are inspected more often than incandescent lamps. It is recommended to inspect fluorescent lamps daily, and clean them from dust and check their serviceability at least once a month.

During operation, it is also necessary to take into account that after the end of the normal service life of a fluorescent lamp (about 5 thousand hours), it practically loses its quality and must be replaced. A lamp that only blinks or glows at one end must be replaced.

built by _____________________________________________________________________

(name of construction and installation organization)

and project number)

by the address: _______________________________________________________________________

(city, street, start and end picket references)

1. Characteristics of the gas pipeline (gas inlet)

The length (for underground and above-ground sections), diameter, operating pressure of the gas pipeline, type of insulating coating of the linear part and welded joints (for underground gas pipelines and gas inlets), number of installed shut-off devices and

other structures ________________________________________________________________

________________________________________________________________________________

________________________________________________________________________________

2. List of attached certificates, technical passports (or copies thereof) and other documents certifying the quality of materials and equipment

________________________________________________________________________________

________________________________________________________________________________

________________________________________________________________________________

Note. It is allowed to attach (or place in this section) extracts from these documents, certified by the person responsible for the construction of the facility and containing the necessary information (certificate number, brand (type), GOST (TU), dimensions, batch number, manufacturer, date of issue , test results).

3. Data on welding gas pipeline joints

Note. The diagram must be drawn up so that the location of each joint can be found from the surface of the earth. To do this, references must be made to permanent ground objects (buildings, structures) of both the gas pipeline itself and its characteristic points (ends, turning points, etc.); The distances between joints, as well as between joints and characteristic points, including intersecting communications, must be marked. Strict adherence to the scale of the diagram is not necessary.

4. Checking the depth of the gas pipeline, slopes, beds, installation of cases, wells, carpets (compiled for underground gas pipelines and gas inlets)

It was established that the depth of the gas pipeline from the surface of the earth to the top of the pipe along its entire length, the slopes of the gas pipeline, the bed under the pipes, as well as the installation of cases, wells, and carpets correspond to the design.

(position, signature, initials, surname)

5. Checking the quality of the protective coating of the underground gas pipeline (gas inlet)

1.* Before laying in the trench, the protective coating of pipes and joints was checked for the absence of mechanical damage and cracks - by external inspection, thickness - by measurement according to GOST 9.602-89 mm: adhesion to steel according to GOST 9.602-89; continuity - flaw detector

2.*Joints isolated in a trench are checked by external inspection for the absence of mechanical damage and cracks.

Position 3 should be excluded

4 * Checking for the absence of electrical contact between the metal of the pipe and the ground was carried out after the trench was completely backfilled “___” ______________ 200__ g

Note. *If the trench was backfilled when the soil froze more than 10 cm during Shubin, then the construction and installation organization must carry out an inspection after the soil has thawed, which must be recorded in the acceptance certificate for the completed construction of the gas supply system facility.

When checking the quality of the protective coating, no defects were found

Head of laboratory ___________________________________________________________

(position, signature, initials, surname)

Representative of the gas industry ___________________________________________________

6. Purge of the gas pipeline, testing it for strength and tightness

Position 1 should be excluded.

2 “___” ___________ 200__ before the strength test, the gas pipeline was purged with air.

3 * “___” ___________ 200__ pneumatic (hydraulic) test performed

gas pipeline strength by pressure MPa (kgf/cm2) with exposure for _____ hours.

The gas pipeline passed the strength test.

4. “___” ___________ 200__, a gas pipeline backfilled to design levels with fittings installed on it and branches to objects up to shut-off devices (or the underground part of the gas inlet) was tested for tightness within ____ hours

Before the test, the underground gas pipeline was under air pressure for ____ hours to equalize the air temperature in the gas pipeline with the ground temperature

Pressure measurements were made with a pressure gauge (differential pressure gauge) in accordance with GOST _______, class.

Data from pressure measurements when testing an underground gas pipeline

Date of testing

Pressure measurements, kPa (mm Hg)

Pressure drop, kPa (mm)

month

number

watch

manometric

barometric

permissible

actual

P(1)

P(2)

B (1)

AT 2)

According to the above pressure measurements, the underground gas pipeline passed the leak test, no leaks or defects were found in places accessible for inspection;

"___"___________ 200__The above-ground gas pipeline (above-ground part of the gas inlet) was tested for tightness by pressure _____ MPa (kgf/cm 2) with exposure for an hour, followed by an external inspection and check of all welded, threaded and flanged connections. No leaks or defects were found. The above-ground gas pipeline (above-ground part of the gas inlet) passed the leak test.

Work producer ______________________________________________________________

(position, signature, initials, surname)

(position, signature, initials, surname)

7. Conclusion

The gas pipeline (gas inlet) was built in accordance with the project developed by

________________________________________________________________________________

(name of design organization

________________________________________________________________________________

and project release date)

taking into account the agreed changes made to working drawings No. ___ - ___________

Construction has started"___"___________ 200__

Construction completed"___"___________ 200__

Chief engineer of SSMU ________________________________________________________________

(position, signature, initials, surname)

Representative of the gas industry ___________________________________________________

(position, signature, initials, surname)

REGULATORY REQUIREMENTS

To maintain the emergency lighting system in good working order, it is necessary to perform periodic checks of the emergency lighting at the site. The requirements for testing emergency lighting are set out in a number of regulatory documents, including international standards.

General requirements for checking the serviceability of emergency lighting

"RULES of the fire regime in the Russian Federation." Approved by Decree of the Government of the Russian Federation dated April 25, 2012 No. 390.

“RULES for the technical operation of consumer electrical installations.” Approved by the Ministry of Energy of the Russian Federation, Order No. 6 dated January 13, 2003.

Emergency lighting testing for centralized emergency lighting systems

EN 50171 Central power supply systems - used for centralized power supply systems.

Testing emergency lighting for uninterruptible power supplies

GOST P 50571-5-56-2013 Low-voltage electrical installations. Part 5-56. “Selection and installation of electrical equipment. Safety systems", IEC 60364-5-56:2009.

Emergency lighting testing for stand-alone signs and luminaires

Federal Law of the Russian Federation No. 123-FZ “Technical Regulations on Fire Safety Requirements” July 22, 2008 (Article 82, Part 9).

GOST IEC 61347-2-7-2014 “LAMP CONTROL DEVICES”. Part 2-7 Particular requirements for battery-powered electronic ballasts used for emergency lighting (autonomous). IEC 61347-2-7:2011.

IEC 62034 Automatic test systems for emergency lighting - used for self-contained emergency lighting luminaires with automatic testing functions.

STANDARD SOLUTIONS FOR CHECKING THE SERVICEABILITY OF EMERGENCY LIGHTING

Modern technologies make it possible to implement various methods of testing emergency lighting. Conventionally, the functions of checking the serviceability of emergency lighting can be divided into local monitoring and central monitoring.

LOCAL MONITORING

Local monitoring is used to individually check each lighting device separately. The solution is implemented by using the manual testing button or the automatic testing function built into the light device - AUTO-TEST.

Manual test button

The simplest and cheapest solution. Using the manual testing button allows you to isolate the luminaire from the mains operating voltage. The button is installed on the body of the light device. When the button is pressed, the function of automatically switching the lamp to emergency operation from the battery is checked. At the same time, the brightness of the display or the luminous flux of the lamp is assessed in order to assess the battery charge level. The main disadvantage of this solution is the high level of labor costs when checking the serviceability of emergency lighting, and the inability to accurately test the operating time of the lamp in offline mode.

Auto test

The automatic testing function is a modern solution and allows you to periodically check the serviceability of emergency lighting for each individual luminaire. An example is LUMI TEST, implemented in Teknoware self-contained luminaires. The serviceability check is performed according to predefined algorithms in the form of short and long tests. Short tests are carried out more often; they trigger a short-term disconnection of the lighting device from the operating mains voltage. Long tests are performed every six months and check the performance of the lamp for maximum operating time in autonomous mode or until the batteries are “completely” discharged. The serviceability status is displayed using a corresponding light indication on the body of the lamp or indicator. The advantage of the auto-test is the convenience of monitoring the serviceability of emergency lighting and low operating costs associated with checking and testing emergency lighting. If luminaires are installed at high altitudes or in hard-to-reach places, using an auto-test may not always be convenient.

CENTRAL MONITORING

Central monitoring automates the process of testing and collecting information about the condition and serviceability of emergency lighting. Implemented by combining light priors into one group. Power lines for lamps, additional data cables, and wireless data transmission devices can be used as information collection channels.

Central monitoring via additional data cable

Autonomous emergency lamps and evacuation signs are combined into a network using an additional data cable. Using a data cable, the lamps are connected to a special controller. The data cable is used to transmit telemetric information about the serviceability of emergency lighting. To perform the functions of monitoring the serviceability of emergency lighting, lighting devices must have a special built-in interface for connecting a data cable.

Central wireless monitoring of autonomous luminaires

One of the most interesting solutions for wireless monitoring of the health of emergency lighting is AALTO Control technology. Inside autonomous lighting devices, a special device is used that receives and transmits information via a radio channel. AALTO Control technology is used only to collect information about the serviceability of emergency lighting and does not affect the operation of the lighting device, ensuring its independent operation. Lamps and signs independently form a single network, sequentially transmitting information from one lighting device to another. Signals easily penetrate walls and ceilings. One AALTO Control system can perform emergency lighting monitoring operations for up to 5,000 luminaires and signs, which can be located in several buildings. Information can be transmitted via the Internet or over a local network to the dispatcher’s computer. The user-friendly software allows you to maintain one log, saving all test data for each light fixture.

Central address monitoring in central battery systems

In centralized emergency lighting systems, power supply to emergency lamps and evacuation signs is carried out through the central unit. Addressable emergency lighting systems implement technologies that allow monitoring the health of lighting devices in automatic mode. Testing the functionality of emergency lighting is based on the use of unique addresses for each luminaire and sign. Various types of tests are performed, each at a specific frequency. Data exchange on test results is transmitted via the power supply lines of the luminaires. Thus, there is no need for additional data cables to organize monitoring. Together with the luminaire test, the central system monitors the charge of the central unit's batteries and also performs all functions required by the EN 50171 standard.

Various interfaces are used to transmit monitoring data on the health of emergency lighting. Depending on the type of interface, data can be transmitted via the Internet, using wired lines via the RS485 protocol, via BACnet or LON protocols to building automation and control systems.

WEBCM & WEBACM

To perform operations to check the serviceability of emergency lighting, a special web module with its own IP address is installed in the central unit of the system. Monitoring is performed through a regular web browser. To perform monitoring operations, additional software can be used - WebACM, connected via Ethernet TCP/IP. The software allows you to place lighting fixtures on the building plan.

WebCM and WebACM allow you to send notifications by email when an emergency occurs; control multiple address systems; manage tests, keep a log of test results; control access for different users.

ACM

ACM is a centralized remote monitoring system that uses a separate network to connect addressable emergency lighting systems. Several address systems can be combined into a separate network and connected to a computer.

Information is transmitted via noise-proof lines using the RS485 protocol. Up to 150 addressable systems can be combined into one network. The length of data transmission lines can reach up to 1 kilometer. The emergency lighting is monitored using additional ACM software.

BACNET

BACnet (Building Automation Control network) is a switching protocol for building automation and standardizes the interaction between different building engineering systems. To perform operations for monitoring the serviceability of emergency lighting, a BACnet interface is installed in the central unit of the system, which allows you to transmit BACnet objects about the serviceability of the system and lighting devices.

Using the BACnet interface, you can run various tests at specified intervals. BACnet is an open protocol and allows the integration of addressable emergency lighting systems with building automation systems.

LON

Central LON monitoring is based on the use of COBA Building Operating Systems. COBA is a software environment for unified automated building management and security systems.


A special module is installed in the central unit of the addressable emergency lighting system. The system consists of an open LON (Local Operation Network) network and a server, to which centralized emergency lighting systems are connected.

DESIGN SOLUTION FOR YOUR FACILITY

Order a design solution for organizing monitoring of the serviceability of emergency lighting and optimal selection of equipment in accordance with the technical and economic requirements of your project. Our company’s specialists will select equipment, prepare specifications and provide a commercial proposal for supply. When developing a design solution, we guarantee full protection of your commercial interests.

For any questions you may have, please call or send a request by mail.

No. of lighting boards Number of lamps in groups Results of checking for correct ignition and combustion of lamps
ShchE No. 1 1 gr. acc. ave.
2 gr. acc. Ave. Ignition according to the project, working properly
ShchE№ 2 1 gr. acc. ave. Ignition according to the project, working properly
2 gr. acc. Ave. Ignition according to the project, working properly
3 gr. acc. Ave. Ignition according to the project, working properly
4 gr. acc. Ave. Ignition according to the project, working properly
ShchE No. 3 1 gr. acc. ave. Ignition according to the project, working properly
2 gr. acc. Ave. Ignition according to the project, working properly
3 gr. acc. Ave. Ignition according to the project, working properly
4 gr. acc. Ave. Ignition according to the project, working properly
ShchE No. 4 1 gr. acc. ave. Ignition according to the project, working properly
2 gr. acc. Ave. Ignition according to the project, working properly
3 gr. acc. Ave. Ignition according to the project, working properly
4 gr. acc. Ave. Ignition according to the project, working properly
ShchE No. 5 1 gr. acc. ave. Ignition according to the project, working properly
2 gr. acc. Ave. Ignition according to the project, working properly
3 gr. acc. Ave. Ignition according to the project, working properly
4 gr. acc. Ave. Ignition according to the project, working properly
ShchE No. 6 1 gr. acc. ave. Ignition according to the project, working properly
2 gr. acc. Ave. Ignition according to the project, working properly
3 gr. acc. Ave. Ignition according to the project, working properly
4 gr. acc. Ave. Ignition according to the project, working properly

Foreman (master) ______________ I. Dubrovin

Customer representative ____________________ T. Nefedov

EXAMPLE OF EXECUTION OF A REPORT FOR CHECKING A LIGHTING NETWORK FOR THE FUNCTIONING AND CORRECT INSTALLATION OF INSTALLATION DEVICES

Certificate of inspection of the lighting network for functioning and correct installation of installation devices

Commission consisting of:

Customer representative:

Representative of the electrical installation organization:

_________________________________________________________________

Conducted an inspection of the installed lighting network. As a result, it was established:

Lighting network:

1. The switching of group boards by phases was carried out in the main switchboard and pantographs in the rooms in group boards according to the project completed by: _________________

_____________________________________________________________________

2. Switches are located in phase wires

Editor's Choice
The post is long, and I’ve been racking my brains trying to figure out how to make something so lean as a dessert without it being applesauce. AND...

Today I cook about half of the cakes in a slow cooker. This is very convenient for me, and gradually many cakes that used to...

Before you start cooking according to the recipe that you like best, you need to choose and prepare the carcass correctly: First,...

Salads with cod liver always turn out very tasty and interesting, because this product goes well with many ingredients...
The popularity of canned squash for the winter is growing every day. Cute, elastic and juicy vegetables, reminiscent in appearance...
Not everyone likes milk in its pure form, although it is difficult to overestimate its nutritional value and usefulness. But a milkshake with...
In this lunar calendar for December 2016 you will find information about the position of the moon, its phases for each day of the month. When favorable...
Supporters of proper nutrition, strictly calorie counting, very often have to deny themselves small gastronomic joys in the form of...
Crispy puff pastry made from ready-made puff pastry is quick, inexpensive and very tasty! The only thing you need is time to...